An award winning project to replace an ozone depleting HCFC based chiller package with an environmentally friendly system has recently been completed for Glaxo SmithKline in Stevenage. We provided the civil/structural engineering designs for the new two storey buildings that house the state of the art, 1MW chiller packages.
The £5m project commenced in 2003, with GSK looking to renew the R22 based refrigerant system in line with the Montreal Protocol which requires refrigerants such as R22 to be fazed out by 2010 due to their detrimental effect on the ozone layer.
The development represents the largest project to date that we have completed through our alliance with Projen.
The project won the ECI ACTIVE Project of the Year Award in 2004 for Managing Contractor Projen, after being nominated by GSK.